108 MOBILIZATION

From SHA MediaWiki
Jump to navigation Jump to search
This is not a legal document. Please see disclaimer for more information.
108.01 DESCRIPTION
Construction preparatory and closing (clean-up) operations that include the movement of personnel, supplies, materials, tools, equipment, and incidentals to, within, and away from the project site collectively for the project and for individual work operations; and the establishment and removal/decommissioning of the Contractor’s offices, buildings, and other facilities necessary to commence, continue, and conclude the work. Perform final clean-up as specified in GP 4.09.
108.02 MATERIALS
Not applicable.
108.03 CONSTRUCTION
Not applicable.
108.04 MEASUREMENT AND PAYMENT
Mobilization and Demobilization will not be measured but will be paid for at the Contract lump sum price. The cost of all required insurance and bonds will be incidental to this item. Payment of the Mobilization and Demobilization item will be made according to the following payment schedule.


Payment of 50 percent of the Mobilization item will be made in the first monthly estimate after the Contractor has established the necessary facilities. The remaining 50 percent will be prorated and paid in equal amounts on each of the next five monthly estimates. The payment will be full compensation for all material, labor, equipment, tools, and incidentals necessary to complete the work.
Payment of the Mobilization item will not be made more than once, regardless of the fact that the Contractor may have, for any reason, shut the work down on the project or moved their equipment away from the project and then back again.
If an item for mobilization is not provided, the cost of mobilization, including the required insurance and bonds, will be incidental to the other items specified in the Contract Documents.